EXPERIENCE IN RISK ASSESSMENT OF UNDERGROUND CONSTRUCTION

L. L. Kaufman, B. A. Lysikov, K. I. Zapolova, I. Zh. Syrachov

Abstract


The article gives examples of underground construction of hydropower station inNepaland sewer tunnel in the USA. These projects pay attention to influence of geotechnical risks and their consequences.

 


Keywords


risk; underground construction; hydroelectric; geotechnical risk

Full Text:

PDF

GOST Style Citations


1. Кауфман, Л. Л., Геотехнические риски подземного строительства [Текст] / Л. Л. Кауфман, Б. А. Лысиков. – Донецк: Норд-Пресс, 2009. – 362с.

2. Allocating the Risk of Subsurface Conditions on Underground Construction Projects [Электрон. ресурс]. – Режим доступа: http://www.ralaw.com/resoursees/documents /Allocating%20Risk

3. Contract Strategics in Construction Projects [Электрон. ресурс]. – Режим доступа: http:// www.atkinson-law.com/cases/Cases Articles/Contract-Strategics.htm

4. Hoek, E. Geotechnical Considerations in tunnel design and contract preparation [Электрон. ресурс] / E. Hoek. – Режим доступа: http: // www.rocscience.com /hoek/references/H 1982.pdf

5. Groundwater risk reqister [Электрон. ресурс]. -Режим доступа: http://www.indygov.org/NR /rdonlyrer/IE9E43CO-7SAO-4D18

6. Jsaksson, I. Model for estimation of time and cosed based on risk evaluation applied on tunnel project [Электрон. ресурс] / I. Jsaksson. – Режим доступа: http://www.diva-portal.org/kth/thesrs /abstract.xsql.dbid





Creative Commons License